River Wilderness

Homeowners Association

 

Home

Board

Documents

Info

 

River Wilderness Road Maintenance Status 2018 - Archive

 

*   Daily Milling/Paving Status

 

   Download  2018  RW Roads Project.pdf

 

We will start on Monday, February 19, 2018 with installing gutter buddies to keep the storm drains clean. The daily milling schedule beginning February 20, is as follows:

 

  -  Grandview Dr., Woodland Terrace, and a portion of Woodland Fern

  -  Woodland Fern, Maple Ridge Dr.

  -  Laurel Oak Lane

  -  Wilderness Blvd. E. (beginning at WBE & LCR intersection

  -  Old Orchard Lane and Lakeside Circle

  -  Wilderness Blvd. E (continuing to WBE & WBE intersection)

-  Road patches and repairs

     1. Entry side only at Old Tampa Entrance (inside the Gate).

     2. 3640 manhole to 3628 on Wilderness Blvd West

     3. 3625 to 3613 Wilderness Blvd West - edge

     4. A strip of Wilderness Blvd West in front of the Maintenance Center

 

The daily paving will follow the same schedule as the milling. The more work we can complete each day the better for all concerned. This schedule will fluctuate with rain days.

 


Revised Schedule as of 02-22-2018


Milling

Feb 19 – Initiaql Staging
**COMPLETED**

Paving

 

Feb 20 - GREEN

Woodland Fern, Woodland Terrace, Grandview Dr.
**COMPLETED**

Feb 26 - GREEN

Woodland Fern, Woodland Terrace, Grandview Dr

Feb 21 - YELLOW

Woodland Fern
**COMPLETED**

Feb 27 - YELLOW

Woodland Fern

 

Feb 28 - LIGHT BLUE

Repairs WBW (north/south)

Feb 22 - RED

Laurel Oak Ln  COMPLETED
WBE  2/3 COMPLETE

Mar 1 - RED

Laurel Oak Ln, WBE

Feb 23 - DRK BLUE

WBE

Mar 1, 2 – DRK BLUE

WBE

Feb 26 - PURPLE

Lakeside Circle, Old Orchard Ln,
remaining WBE

Mar 2 - PURPLE

Lakeside Circle, Old Orchard Ln,
remaining WBE

Feb 26, 27 - LIGHT BLUE
Main Entrance,
WBW (north/south)

Mar 5 - LIGHT BLUE

Main Entrance Repair

 

 

 

 

ATTENTION RIVER WILDERNESS RESIDENTS

WHAT YOU NEED TO DO:

 

Emergency vehicles will have access at all times. Additionally, Emergency golf cart transportation will be available from the nearest street in difficult situations, though delays may occur.

 

All irrigation must be turned off for the entirety of the project. It is okay to hand water your planting beds during the process as long as the runoff does not reach the roadway.

 

You must postpone any major projects such as construction, re-roofing, driveway pavers, dumpster pick-up and /or delivery, etc. until April 1 if you live on the streets being repaved.

 

Please be aware of the crew and where they are working every day. You will be allowed to drive your regular vehicles to and from the property. Expect delays as the equipment passes your house.

 

DO NOT park any vehicle on the roadways being milled or paved as they will be towed at the owner’s expense. Do not park on the grass. "On the Road Parking" will be permitted on Little Country Road during the milling and paving process for your street.

 

To avoid your vehicle collecting dust, you should park in the garage or off property.

 

Heavily weighted down tarps can be used to protect driveways.

 

To avoid dust in the home, keep all windows closed during the milling and paving project.

 

Inform vendors and personal guests, as well as nurses, home health care aides, service people etc. so that they are aware of the milling schedule as well. They should expect delays on the days that your street is being milled or repaved.

 

Garbage and Recycle pick-up will be diverted if it occurs on a day your street is being milled or paved.

 

Large vehicles and or trailers will not be allowed on a street when milling or paving equipment is on that street. These include lawn service vehicles and moving vans.

 

Reschedule all your vendors and all your deliveries (including Fed-Ex and UPS) until at least 7 days after the paving is complete. Or you could arrange to pick up deliveries at their nearest offices.

 

The entrance side of the Old Tampa Road gate will be closed for a part of one day during the second week. Flagmen will be stationed to redirect traffic.

 

If possible, Wilderness Blvd West, Savannah Lakes & Islands Residents should use the Ft. Hamer Road entrance from February 28 through March 5 and should inform all their vendors and visitors to also use that gate during those dates. Please be aware that longer vehicles cannot navigate the circle on Island Estates Drive without doing damage to properties. Residents will need to postpone these services for these days. We expect the Old Tampa Road entrance and Wilderness Blvd. West to be impacted for only one to two days during this time but cannot yet specify an exact date.

 

Do not power wash driveways along the repaved roadways from February 19 until April 1. Wait at least 7 days after paving is complete to wash them with a hose


What to Expect – The Process


1  The Milling Process



2  Primer/Tac Oil



3  Paving the Road