Daily Milling / Paving Status - Archive

 

Date

Location

Status

Consultants
Report

Feb 19

RW

Staging Complete

Day 1 Staging

Feb 20

Grandview Dr
Woodland Ter
Woodland Fern

Milling Complete
Milling Complete
Milling Complete, from LCR to
Woodland Fern & Maple Ridge Circle


Day 2 Milling

Feb 21

Woodland Fern
Maple Ridge Spur
Laurel Oak Ln

Milling Complete
Milling Complete
Postponed to Feb 22


Day 3 Milling

Feb 22

Laurel Oak Ln
Wilderness Blvd East
(LCR to Lakeside Circle)

Milling Complete
Milled 3/4 of WBE from LCR
to the northern intersection
of WBE & Lakeside Cir.


Day 4 Milling

Feb 23

Wilderness Blvd East

(LCR to Lakeside Circle)
Old Orchard
Lakeside Circle

Milling Complete
 
Milling Complete
Milling 3/4 complete


Day 5 Milling

Feb 24
Feb 25

 

No Road work

 

Feb 26

Lakeside Circle
Old Orchard
WBE
Grandview Dr.
Woodland Ter.
Maple Ridge Spur
Woodland Fern
WBW Repairs

Milling Complete
Milling Complete
Milling Complete
Paving Complete
Paving Complete
Paving Complete
Paved up to Oak Ridge
Milling Complete



Day 6

Feb 27

Woodland Fern
Laurel Oak
WBE at LCR

Paving Complete
Postponed to Feb 28
Postponed to Mar 1


Day 7

Feb 28

Laurel Oak Ln
Old Orchard
Lakeside Circle

Paving Complete
Paving Complete
Paved 1/2 of road


Day 8 Paving

Mar 1

Lakeside Circle
WBE

Paving Complete
Paved from WBE & WBE
 to 2995 WBE


Day 9 Paving

Mar 2

Remaining WBE
WBW Repairs
Main Entrance

Paving Complete
Paving Complete
Paving Complete


Day 10 Final

Mar 3

RW

General Clean Up

 

 

Revised Order as of 02-22-2018
All Paving Completed 03-02-2018

GREEN
Grandview Dr.,
Woodland Terrace,
Woodland Fern
**Milling Complete**
**Paving Complete**

 

 


YELLOW
Woodland Fern
**Milling Complete**
**Paving Complete**

RED
Laurel Oak Ln
Paving Complete
WBE
(LCR to Lakeside Circle)
**Milling Complete**
**Paving Complete**

DRK BLUE
WBE
**Milling Complete**
**Paving Complete**

PURPLE
Lakeside Circle
Old Orchard Lane
**Milling Complete**
**Paving Complete**

LIGHT BLUE
Main Entrance,
WBW (north/south)
**Milling Complete**
**Paving Complete**